Location:
48 Ha’alia Hashnia st. Herzlia, Israel
Products:
MCI-2020
The Problem:
This 50 year old water tower developed corrosion cracking, spalling and water leaks necessitating repair.
The Solution:
First, all delaminated, unstable concrete was removed. Exposed reinforcing steel was cleaned and new concrete patches were placed. The entire structure was then treated with two coats of MCI®-2020 with a total dosage rate of 3.68 square meters per liter (150 square feet/ gallon). Following MCI®-2020 application, bi-component PU paint was applied.
Constructor: Reshef H. Contractors (1990) LTD
Date: 2008
Entrepreneur: Mey-Herzlia LTD
Engineer: Horwitz Buch Engineering LTD